Vulcan reports new construction milestones at Lionheart
In its quarterly report, Vulcan said initial bulk earthworks and relocation of a 110 kV line were complete at the Landau lithium extraction site. Construction of the first pipeline-network section had started, while the Frankfurt lithium chemicals plant passed its 30% design review. Lionheart remains under construction, with industrial production targeted from 2028.
- Source date
- 30 Oct 2026 · P2