E3 Lithium prepares phase three of Clearwater demonstration programme
E3 says phase two of its demonstration programme is nearing completion. It is preparing phase-three lithium carbonate production and expanding the DLE system with a commercial-sized column to collect operating data. Engineering work is advancing toward completion in 2027. This remains a demonstration programme, not a commercial plant start-up.
- Source date
- 29 Sept 2026 · P2